Repaving work to begin Sept. 4 at El Cerrito Plaza Station

We will be repaving the bus intermodal area at El Cerrito Plaza station. This work will start on Sept. 4, the day after Labor Day, and will last about four weeks. The work is staged into two phases; each will last approximately 14 calendar days.

Phase 1 will be on the East side of the station and Phase 2 will be on the West side of the station. During each phase, buses that normally use the closed section will be relocated to the opposite side of the station.  Please pay attention to signage in the area. All parking rules will be enforced. There will be temporary taxi parking in 3 stalls in the lot. To view a map download the passenger bulletin.