For more information about the BART Warm Springs Extension project, please call the Project Information Line at (510) 476-3900 or email bartwarmspringsextension@bart.gov. You can also visit our Community Relations Field Office at 1320 Stevenson Boulevard, in Fremont. The Field Office is located in Fremont Central Park off of Stevenson Boulevard. Office hours are 8 am to 5 pm, Monday through Friday.
Construction Photo Slideshow
Construction Notification 37: Expanded Construction Activities Scheduled
Estimated Start Date
January 2012
Summary of Activity
Activities related to the BART Warm Springs Extension project are set to expand south of Central Park all the way to the Warm Springs Station site near South Grimmer Boulevard.
Estimated Duration
Three months
Impacts
Some noise, dust and hauling
Construction Notification 10: Soil Hauling Operation to Begin Along Driscoll Road
Estimated Start Date
March 29, 2010
Summary of Activity
Contractors will begin soil hauling operations using Driscoll Avenue and Paseo Padre Parkway. Soil will be stored in the field east of Fremont Central Park, just south of the golf course between the Union Pacific Rail Road tracks. Hauling hours are 8:30 am to 1:30 pm and 2:30 pm to 7 pm, Monday through Friday. Additional hauling will be required throughout the duration of the project.
![]() |
| Click the image to enlarge it. |
Estimated Duration
Intermittent work through 2012
Impacts
Expect increased dust, noise and inconvenience from construction equipment.
Construction Notification 6: Fremont Central Park Subway Construction Work to Begin on Stevenson Boulevard
Summary of Activity
Construction of the Fremont Central Park Subway will begin in mid-December 2009. This work will require two phases of lane reductions on Stevenson Boulevard between Guardino Drive and Civic Center Drive. Traffic will be reduced to one lane in each direction on Stevenson Boulevard as follows:
Phase 1 – December 2009 through Summer 2010: One lane of traffic in each direction on the northern side of Stevenson Boulevard. The westbound bike lane on the northern side of Stevenson Boulevard will remain in service. Automobiles and bicycles will share the eastbound lane of traffic through the area.
Phase 2 – Fall 2010 through Spring 2011: One lane of traffic in each direction on the southern side of Stevenson Boulevard. The eastbound bike lane on the southern side of Stevenson Boulevard will remain in service. Automobiles and bicycles will share the westbound lane of traffic through the area.
The construction work will include:
- Removing the median between Guardino Drive and Civic Center Drive
- Repaving and striping Stevenson Boulevard
- Constructing the subway
Anticipated general work hours are 7 am to 7 pm, Monday through Friday, with some work on Saturday as necessary. Work hours in the Lake Elizabeth area are 7 am to 10 pm, Monday through Friday, and 8 am to 6 pm on Saturday.
![]() |
| Phase 1 Lane Revisions (Click the image to enlarge it.) |
![]() |
| Phase 2 Lane Revisions (Click the image to enlarge it.) |
If you have questions regarding this activity, please contact the Project Information Line at (510) 476-3900 or email bartwarmspringsextension@bart.gov.
Notification Archive
Choose a notification below for full details.
Notification 36: Sheet Pile Driving Set to Resume
Notification 35: Final Restoration of South Shore Lake Elizabeth Pedestrian Pathway
Notification 34: Change to Pedestrian Pathway
Notification 33: Temporary Closure of Stevenson Boulevard
Notification 32: Temporary Closure of Eastbound Stevenson Boulevard
Notification 31: Series of Detours Planned as Part of Restoration of Stevenson Boulevard
Notification 30: Expected Delays on Westbound Stevenson Boulevard
Notification 29: Temporary Reconfiguration of Pedestrian Pathway
Notification 28: Temporary Reconfiguration of Pedestrian Pathway
Notification 27: Temporary Closure of Eastbound Stevenson Boulevard
Notification 26: Temporary Closure of Stevenson Boulevard
Notification 25: Temporary Closure of Stevenson Boulevard
Notification 24-A: Temporary Closure of Westbound Stevenson Boulevard Postponed
Notification 24: Temporary Closure of Westbound Stevenson Boulevard
Notification 23: UPRR Crossing Through Central Park No Longer Available
Notification 22: Temporary Closure of Stevenson Boulevard
Notification 21: New Pedestrian Pathway Detour
Notification 20: Sheetpile Driving Set To Resume
Notification 19: New Dog Park is Open
Notification 18: New Basketball Court is Open
Notification 17: Subway Construction Work Moves Across Stevenson Boulevard
Notification 16: Construction to Begin Behind Archstone Apartment and Business Complex
Notification 15: Temporary Closure of Stevenson Boulevard
Notification 14: Fish Capture and Release
Notification 13: Construction to Begin in Lake Elizabeth: New Pedestrian Detour Path Open
Notification 12: New Tennis Court Parking Spaces Available
Notification 11: New Parking Spaces Available
Notification 9: Construction to Begin Between Walnut Avenue and Stevenson Boulevard
Notification 8: Dog Park and Basketball Court Entrance Detours to Begin
Notification 7: Phase 1 of Softball Field Access Revisions
Notification 5: Movement of Large Equipment in Fremont Central Park
Notification 4: Mobilization of Equipment and Start of BART Subway Construction
Notification 3: Tennis Center Parking Lot Construction
Notification 2: Tree and Shrub Removal
Notification 1: Subway Contract Notice to Proceed
Last Updated: February 2, 2012