Single Tracking Alert: Late night rail work on the Yellow Line in Contra Costa County (next work dates: November 19-20)

BART is performing rail destressing on the Yellow Line in Contra Costa County. To create a safe work space for our crews, BART will reduce service from two tracks to one while the work is taking place. The work is scheduled to start at midnight and continue until BART service begins the next morning. Riders can anticipate delays of 20-30 minutes on work nights. The next location for this rail maintenance work is between Lafayette and Walnut Creek stations November 19-20, 2026.

Dates scheduled for this project include:

*November 19-20

*November 23

*December 3-5

*December 7

*December 17-19

*December 21

(This article is being continually updated throughout the duration of the project.)