Search Results
Installation work to begin Wednesday, May 7 for Next Generation Fare Gates at North Berkeley Station
On Wednesday, May 7 BART will begin the installation of Next Generation Fare Gates on the concourse level of North Berkeley Station. The installation work will happen in stages so riders can continue to use the remaining gates while new ones are being installed. A temporary gate will also be installed to support entry and exit. There will be additional BART staff as well as signage to direct riders to the open gates. The installation of each new set of gates is expected to take up to two weeks to complete. The work to replace all three sets of fare gates at North Berkeley Station is expected to continue into June.
A temporary barrier will be installed around each set of gates when it is ready to be removed to provide a safe workspace for the installation team as well as to protect riders from construction. The work will not delay train service, but riders may experience a few extra minutes wait to pass through the gates during peak travel hours.
The latest work comes after BART has successfully installed Next Generation Fare Gates at 29 stations across the system. All 50 BART stations will have new fare gates by the end of 2025. You can learn more about BART’s Next Generation Fare Gates project here.
Installation work to begin Wednesday, May 21 for Next Generation Fare Gates at 19th Street Station
On Wednesday, May 21, BART will begin the installation of Next Generation Fare Gates on the concourse level of 19th Street Station in Oakland. The installation work will happen in stages so riders can continue to use the remaining gates while new ones are being installed. There will be additional BART staff as well as signage to direct riders to the open gates. The installation of each new set of gates is expected to take up to two weeks to complete. The work to replace all four sets of fare gates at 19th Street Station is expected to continue through June.
A temporary barrier will be installed around each set of gates when it is ready to be removed to provide a safe workspace for the installation team as well as to protect riders from construction. The work will not delay train service, but riders may experience a few extra minutes wait to pass through the fare gates during peak travel hours.
The latest work comes after BART has successfully installed Next Generation Fare Gates at 35 stations across the system. All 50 BART stations will have new fare gates by the end of 2025. You can learn more about BART’s Next Generation Fare Gates project here.
Bus Bridge and Red Line Cancellation Alert: Free buses replace trains between Rockridge, MacArthur, and 19th Street stations on select weekends
(October 2 update): The track shutdowns that had been planned for two weekends in October and November between Rockridge, MacArthur, and 19th Street stations have been postponed until 2025. The postponement will allow BART to focus on other priorities to improve reliability and limit future disruptions. We also continue to evaluate lessons learned from the first shutdown weekend in June, as we plan to adjust our approach and execution. BART’s goal remains to minimize short term impacts on riders by maximizing work efficiency.
BART crews have begun the process of replacing a series of interlockings between Rockridge, MacArthur, and 19th Street stations. Free buses will replace trains between Rockridge, MacArthur, and 19th Street stations on 18 non-consecutive weekends over the next three years. Riders can expect delays of 40 minutes in the area on those work weekends. There will be no Red Line service on these weekends but the Orange line will serve Richmond riders.
Additional service impacts on all work weekends for this project include:
*Yellow Line will run 20-minute service.
*Orange/Blue/Green Lines will run 30-minute service (usually 20 minutes but not possible given project constraints).
*Service to/from Millbrae will be via the Yellow Line.
*All train schedules will be different from the normal weekend timetables. Please check the Trip Planner to see the new train departure times (use the impacted dates of service when planning).
*Due to the new schedule, the last train departures of the night may be earlier than the regularly scheduled departures.
*MacArthur Station will be open for southbound Orange Line stops from Richmond. No Yellow Line service to MacArthur (Yellow line trains end a Rockridge).
*Orange Line bus bridge will operate between MacArthur and 19th St.
*Yellow Line bus bridge will include buses that go directly between Rockridge and 19th St as well as buses that also stop at MacArthur.
*Lower level platforms at both 12th and 19th Street stations will be out of service.
*All buses used for the bus bridge will be outfitted with racks for bicycles. You can also bring traditional bicycles onto the buses if space allows. Please avoid bringing motorized bikes or eBikes to the bus bridge as they may not be allowed on the buses.
*It might be faster to ride your bike between stations than to take the bus bridge. It might also be faster for Richmond Line riders to ride their bikes directly to 19th Street and take BART to their final destination from there.
Interlockings are a vital part of the BART system. They are segments of the railway that allow trains to safely move from track to track. Shutting down train service in the work area ensures a safe workspace for the project team. Work on this project will happen on select, non-consecutive weekends into 2026.
BART crews will make the most of their time in the system by taking on as many trackway improvement projects as possible on the weekends when this portion of the system is closed to trains. In addition to replacing interlockings, the team will also replace traction power cables, install new train control equipment, install new digital display signs at underground stations up to Berkeley and 12th Street/Oakland City Center, manage vegetation that could impact service, and do deep station cleaning.
This will be one of the most challenging rebuilding projects that BART has ever undertaken because of the location of the project. With limited workspace, crews will be unable to use a crane or other heavy equipment to lift track components into place. Instead, workers will transport all materials on rail and assemble larger components by hand. The equipment being replaced is decades old and has outlived its design life. Riders will enjoy a smoother, safer, more reliable, and quieter ride once this project is complete. You can get more details on this project from this staff presentation to the BART Board of Directors.
This project is part of BART’s overall effort to improve the safety and reliability of the 131-mile, 50 station system. There are now more rebuilding projects happening across BART than at any point in its 50-year history. You can learn more about the progress of this work by reading the 2023 Measure RR Annual Report published by the independent Measure RR Bond Oversight Committee.
You can keep up with the latest updates for trackway repair projects that impact service by going to our Alerts and Advisories page.
Learn more about the project with our Frequently Asked Questions (FAQ) page. Also, check out our podcast for an in-depth discussion about the project, its challenges, and long-term benefits for riders.
*This article was originally published May 1, 2024.
Installation work to begin October 11 for Next Generation Fare Gates at San Francisco International Airport Station
BART will begin the installation of Next Generation Fare Gates on Friday, October 11 at San Francisco International Airport Station. The station has a total of four sets of fare gates, two on the upper level and two on the lower level. Workers will replace one set on each level of the station simultaneously. While this work is being done, a set of the old gates will remain open for riders on each level. There will be signage to direct riders to the open gates. There will also be additional staff on site to help direct riders. Once the installation of the first two sets of new gates is complete, work will begin on replacing the third and fourth arrays.
A temporary barrier will be installed to provide a safe workspace for the installation team as well as to protect riders from construction. Each new array is expected to take up to two weeks to install. The latest work comes after BART successfully installed Next Generation Fare Gates at 24th Street Mission, Antioch, Civic Center, Fruitvale, Oakland International Airport, Richmond, and West Oakland stations.
All BART stations will have new fare gates by the end of 2025. You can learn more about BART’s Next Generation Fare Gate project here. Riders can provide feedback about the new gates at bart.gov/comments.
Installation work to begin Friday, June 6 for Next Generation Fare Gates at Bay Fair Station
On Friday, June 6 BART will begin the installation of Next Generation Fare Gates on the concourse level of Bay Fair Station. The installation work will happen in stages so riders can continue to use the remaining gates while new ones are being installed. A temporary gate will be installed to support entry and exit. There will be additional BART staff as well as signage to direct riders to the open gates. There will also be a service gate available for those riders who would typically use an accessibility gate.
The installation of each new set of gates is expected to take up to two weeks to complete. The work to replace all three sets of fare gates at Bay Fair Station is expected to continue into July.
A temporary barrier will be installed around each set of gates when it is ready to be removed to provide a safe workspace for the installation team as well as to protect riders from construction. The work will not delay train service, but riders may experience a few extra minutes wait to pass through the gates during peak travel hours.
The latest work comes after BART has successfully installed Next Generation Fare Gates at 36 stations across the system. All 50 BART stations will have new fare gates by the end of 2025. You can learn more about BART’s Next Generation Fare Gates project here.
Alert: Red line cancelled on Wednesday, June 26th due to maintenance vehicle derailment
Update: June 26, 2024 7:15 am
Crews moved our maintenance vehicle out of the way last night.
The Red Line returned to service when we opened this morning.
We apologize for the inconvenience it caused and we thank our riders for their patience.
--------------------------------------------------------------------------------------------------------------------------------------
At about 3:30am on Wednesday, June 26, 2024, a BART track maintenance vehicle derailed near 19th Street/Oakland Station blocking one set of tracks.
No BART stations are closed but the Red Line is cancelled. We anticipate the Red Line to be cancelled all day but back in service tomorrow. Red line trains will show as cancelled in real time departures and the Trip Planner.
- San Francisco bound passengers coming from the Richmond direction who would normally take a Red Line train should take an Orange Line Berryessa train and transfer to a Yellow Line San Francisco train at MacArthur Station.
- Millbrae riders should take the Yellow Line.
- Orange Line trains coming from Richmond will need to divert to West Oakland after 12th St. Station and then turn back towards the Berryessa direction. So they will run: 12th St, West Oakland, Lake Merritt, and so on. Orange Line trains coming from Berryessa don’t need to do this.
- Platform 2 at 19th Street/Oakland Station is closed and trains may be stopping at a different platform that usual at 12th and 19th St stations.
The incident is not causing major delays.
BART Service Alerts are available via email, text, or customized push notifications in our official BART app.
Text and email opt-in: http://cloud.info.bart.gov/signup
On our app, select the profile icon and then notification settings. Set as many as you need for exactly when you typically ride BART. You will get push notifications of our alerts only during the selected times.
Outreach begins on SF escalator and entrance improvements
Thanks to State Proposition 1B and the City of San Francisco, BART has received $12 million that gives us the opportunity to make extensive improvements to escalators and entrances at some of our downtown San Francisco stations. We have entered into a planning and design process to determine the best use of
Link21 Program awarded $11.3 million in new state funding to advance planning of second transbay train crossing
The Link21 program, which is envisioned in the California State Rail Plan, has been awarded $11.3 million by a state program that funds transformative transit and rail capital improvements to significantly reduce emissions of greenhouse gases, vehicle miles traveled, and congestion. The California State
Work to install Next Generation Fare Gates to get underway at four stations
BART is making more progress with its effort to replace aging fare gates at all 50 stations by the end of this year. This week BART will begin installing Next Generation Fare Gates at Concord, Glen Park, and San Leandro stations. Work is also scheduled to begin next week at El Cerrito Plaza Station. The latest work comes after BART has successfully installed Next Generation Fare Gates at 22 stations across the system.
The work will not impact train service, but riders may experience a few extra minutes wait to pass through the fare gates during peak travel hours.
You can learn more about BART’s Next Generation Fare Gates project here
Regular train speeds return to Oakland core service area
BART riders will benefit from faster train speeds through the downtown Oakland core service area following the repair of an essential power substation. Last summer, the substation located near 19th Street Station failed after experiencing a fault, requiring BART to realign power distributions from nearby redundant substations while repairs were being made. This configuration required BART to run trains at slower speeds in the track areas approaching MacArthur, 19th Street, and 12th Street stations. Trains were also metered into these stations, causing frequent but short train holds. This service plan caused delays of about three minutes, but those delays could compound when other incidents occurred in the system.
Crews have been diligently working to get the substation back to full operations, and late last week, the substation was successfully brought online. Over the weekend, normal speeds were restored. Trains no longer need to run at 27 mph through the area and are now travelling up to 70 mph.
2025 will be an important year for fortifying and expanding BART’s power substations. Another substation located east of the Transbay Tube is being fully renovated, and two new power substations located near Civic Center and Montgomery stations will also be coming online this year. This work plays a key role in ensuring that BART’s power system infrastructure is robust, reliable, and ready for the future.