San Francisco Station Entrances

Powell entrance by Maria J. Avila

Canopy masthead

UPDATE (July 2020)

Dear Market Street Neighbors & Stakeholders:

The BART Market Street Escalator Project was awarded and began in mid-2019.  The contractor has been actively assessing and surveying existing equipment and conditions since that time.  Escalator units are being fabricated off site and upon delivery, crews will work to install these new units.

In the weeks ahead the contractor will begin work on replacing the first three of 41 escalators at two of the four downtown stations in San Francisco.  The total contract will include installation of 23 street-level escalators, and 18 platform-level escalators at all four downtown stations. 

BART entrances will remain open and accessible to transit riders during escalator installations. The BART Market Street Escalator Project is working in close coordination with the BART Market Street Canopy Project to synchronize construction timelines.  An escalator may only be installed once a canopy has been constructed.
  
The first installation of escalator units will be at the following locations:
  
(Outside Station) 
Powell St. Station – 4th & Market / Ellis Street at corner near Diesel Store (North side of Market Street)

(Outside Station) 
Civic Center Station – 7th & Market near corner CVS Store (South side of Market Street)

(Inside Station) 
Powell St. Station – Platform escalator inside station at the west end near Westfield Shopping Center

Upcoming Activities

On July 20 the contractor will begin installation of three barricades which will be used for laydown / storage areas on the concourse level, inside the Powell Street & Civic Center stations. The 3 escalators listed above will remain in service at this time, and pedestrian traffic inside the station will not be affected. Project information about the associated construction will be displayed on the outside of the storage barricade.

On the following days BART’s contractor will take the first three escalators out of service and start installation of barricades around the top, incline and bottom of each escalator unit.  
•    Powell St. / 4th & Market – July 27
•    Powell St. / Platform Escalator – July 30
•    Civic Center / 7th & Market – August 3
*Dates subject to change

These escalators will remain out of service for 6 months while the contractor works to install the new escalator units.   

BART will need to close the Powell St. Station entrance for two weekends later in Summer 2020 to safely move the new escalators in place.  We will notify neighbors and riders prior to these temporary weekend closures.  Thank you for your patience as we work to complete this important project.    

If you need language assistance services, please call BART’s Transit Information Center at (510) 465-2278.
如需語言援助服務,請致電 BART 公共交通資訊中心,電話號碼為 (510) 465-2278.
통역이 필요하시면, BART 수송 정보 센터 (510) 465-2278로 전화해 주십시오.
Si necesita servicios de asistencia de idioma, llame al centro de información de tránsito del BART al (510) 465-2278.
Nếu quý vị cần các dịch vụ trợ giúp ngôn ngữ, xin gọi cho Trung Tâm Thông Tin Chuyên Chở Công Cộng của BART tại số (510) 465-2278.
Kung kailangan mo ang tulong ng mga serbisyo ng wika, paki tawagan ang BART Transit Information Center na (510) 465-2278.


On January 23, 2020, the BART Board of Directors approved a contract to construct 22 canopies over entrances at BART stations along Market St. in downtown San Francisco.

Two canopies that were completed in November 2018 have proven to be successful in closing the entrances when BART is not open for service, addressing security and maintenance concerns and ensuring that employees who open the entrances are safer. One of the new canopies is above the Powell Street Station (north side of Market and Ellis Streets) and the other above the Civic Center Station (south side of Market and 7th Streets).

Each canopy includes a real-time digital display that shows train arrival times, a retractable gate, LED lighting and security cameras. 

Construction will begin Spring 2020. The entire project will take 7 years because no more than one entrance will be under construction at each station at one time in order to reduce access impacts to stations.

The contract approved by the Board includes purchasing and installing 19 canopies for $64 million as the base and includes options for 3 additional canopies one funding is identified.  The plan also includes incorporating local art into the ceiling surface material. The project to install canopies is funded by voter approved Measure RR funds, San Francisco Prop A funds, and state Prop 1A funds.|

(Click on the graphic below for a PDF version.)

Canopy Escalator Project Graphic

The canopy project is in conjunction with the Market Street Escalators Renovation Project.  That project, approved in March 2019 for $96.5 million, will install and replace 41 escalators at Embarcadero, Montgomery St., Powell St., and Civic Center stations. Twenty-two of the escalators that will be replaced extend from the street to the concourse levels of the stations while 18 connect concourses with station platforms. 

This Market Street Escalators Renovations Project will enhance rider safety and escalator reliability.  A key provision of the program requires the contractor to maintain a reliability rate of at least 96% for the new escalators during the life of the nearly ten-year contract. It’s anticipated BART can complete work on six escalators per year. The first escalators are expected to be delivered for installation in spring 2020.

The canopies will not only protect the new escalators from the wear-and-tear of elements like rain and wind-swept debris, but they will provide an added layer of station security and cleanliness through motorized gates that allow the entrances to be locked at street level when stations are closed. The added protection from the existing canopy in Oakland has reduced escalator down time by about 30%.


Ribbon cutting Powell

Powell Street Station: Ellis and Market Street Entrance

On November 6, 2017, our contractor built a barricade around the entrance to Powell Street Station located at Ellis & Market streets on the north side. The entrance was closed for the construction of the new protective canopy and was opened in a ribbon-cutting ceremony on November 13, 2018.

Civic Center Station: 7th and Market Street south side Entrance 

On Monday, December 11, 2017 our contractor built a barricade around the entrance to Civic Center/UN Plaza Station located at 7th and Market streets on the south side. 

Like the Powell Street Station canopy, the Civic Center canopy will include a digital display to show train arrival times, new security grille, new LED lighting, security cameras, and other improvements. The Civic Center canopy was opened on November 13, 2018.


You can get automated BART Service Advisories (BSA) on your phone. BART offers both email and text options. To sign up for BSAs, please visit us at www.bart.gov/alerts

Follow us on Twitter @sfbart for news or @sfbartalert for automated service advisories.

If you need language assistance services, please call BART’s Transit Information Center at (510)465-2278.

如需語言援助服務,請致電 BART 公共交通資訊中心,電話號碼為 (510)465-2278.

통역이 필요하시면, BART 수송 정보 센터 (510) 465-2278로 전화해 주십시오.

Si necesita servicios de asistencia de idioma, llame al centro de información de tránsito del BART al (510)465-2278.

Nếu quý vị cần các dịch vụ trợ giúp ngôn ngữ, xin gọi cho Trung Tâm Thông Tin Chuyên Chở Công Cộng của BART tại số (510)465-2278.

Kung kailangan mo ang tulong ng mga serbisyo ng wika, paki tawagan ang BART Transit Information Center na (510)465-2278.

  • Please Contact Tim Chan (tchan1@bart.gov) with any questions or comments.